Burndown Chart

Updated 2 min read

Share this page

Send the link, quote the definition with a link back, or show it as a card on your own site.

https://softwaredictionary.org/terms/burndown-chart

In short

A burndown chart is a graph that shows how much work remains in a sprint or release over time, so a team can see at a glance whether it is on track to finish.

What is a burndown chart?

A burndown chart is a simple graph of remaining work over time. The vertical axis shows the work left, measured in story points, tasks, or hours, and the horizontal axis shows the days of a sprint or the sprints of a release. If things go well, the line burns down to zero by the end, and a straight diagonal ideal line from the starting total to zero shows the pace needed to finish on time.

Each day the team, or its tracking tool, records how much work is left and adds a point to the chart. When the actual line stays above the ideal line, the team is behind; when it is below, the team is ahead. A flat stretch means nothing was finished, often because work is stuck in progress or blocked, and a sudden rise means new work was added. A sprint burndown tracks one sprint day by day, while a release burndown tracks the remaining points across several sprints.

A burndown chart is like a fuel gauge on a road trip: one glance tells you whether you will reach the destination or need to change something. Teams look at it during daily standups and sprint reviews because it makes progress visible without a status report. It is most honest when it counts only work that is fully done, because counting half-finished items hides risk until the last days of the sprint.

A burndown chart is often confused with a burnup chart. A burnup chart shows completed work rising toward a separate line for total scope, so it makes added scope obvious, while a burndown mixes progress and scope changes into one line. A burndown is also different from velocity: velocity is how much work gets done per sprint, while a burndown shows how much remains within a timeframe. Either way, the chart is a conversation starter for the team, not a performance measure.

Key takeaways

  • A burndown chart plots remaining work against time.
  • An ideal line from the total to zero shows the required pace.
  • Flat stretches suggest blocked work; upward jumps mean added scope.
  • Sprint burndowns track days; release burndowns track sprints.
  • A burnup chart shows completed work and total scope as separate lines.

Example

Burndown data for a 10-day sprinttext
Sprint 14 burndown: 40 story points committed, 10 working days

Day        0   1   2   3   4   5   6   7   8   9  10
Ideal     40  36  32  28  24  20  16  12   8   4   0
Actual    40  38  33  33  33  27  22  16  11   6   2

Days 2-4: the actual line is flat, so a story was probably blocked.
Day 10: 2 points remain, so one small story returns to the product backlog.

Readers ask

What is the difference between a burndown chart and a burnup chart?

A burndown chart shows remaining work going down toward zero. A burnup chart shows completed work going up toward a separate total-scope line, which makes it easier to see when scope was added.

What does a flat line on a burndown chart mean?

It means no work was completed during that period. Common causes are blocked items, too much work in progress at once, or tasks that are too large to finish in a day or two.